Item 17AGENDA ITEM NO. 17 AGENDA STAFF REPORT City of West Covina I Office of the City Manager DATE: June 21, 2022 TO: Mayor and City Council FROM: David Carmany City Manager SUBJECT: FISCAL YEAR 2021-22 CAPITAL IMPROVEMENT PROGRAM STATUS UPDATE RECOMMENDATION: It is recommended that City Council receive and file the Fiscal Year 2021-22 Capital Improvement Program (CIP) Projects status update. BACKGROUND: A capital improvement program (CIP) is a plan, usually four to ten years, which identifies capital projects and equipment purchases, provides a planning schedule and identifies options for financing the plan. The plan provides a link to the annual budget. State planning law requires that the City Planning Commission review the CIP to ensure that it is consistent with the General Plan. Project delivery is the key. As part of the process, the majority of the CIP projects that are fully funded are required to go through complex and often lengthy steps leading into their implementation and construction phase. The steps include: project planning, scope of improvements, preliminary cost estimating, design phase which often requires issuing Request for Proposals (RFPs) for design consultant selection, preparation of bid documents which comprises construction plans, specifications and cost estimates, authorization to bid, bidding, bid evaluation, recommendation for award of construction contract, and finally construction. DISCUSSION: The purpose of this report is to provide an update on the Capital Improvement Projects for the City. Please see attached FY 2021/22 Capital Improvement Projects (CIP) Matrix (Attachment No. 1). Prepared by: Okan Demirci, PE, QSD/P Additional Approval: Paulina Morales, Assistant City Manager Attachments Attachment No. 1 - FY 2021-22 Capital Improvement Project Matrix CITY COUNCIL GOALS & OBJECTIVES: Protect Public Safety Maintain and Enhance City Facilities and Infrastructure Enhance City Image and Effectiveness A Well -Planned Community ATTACHMENT NO. 1 CITY OF WEST COVINA FY 2021/22 Capital Improvement Projects (CIP) Engineering Department Re don OW M22 PROJ. NO PROJECT CATEGORY STATUS PROJECT BUDGET MILESTONES I UPDATES 22023 City Council Restrooms (Men and Women) Improvements Facilities Construction $ 130,250 Anticipated completion is August 2022 22007 Cortez Park- Park Improvements - New playground Parks, Playgrounds and Fields Construction $ 387,354 Anticipated completion is July 2022 21005 PalmView, Aroma & Walmerado Parks- New Pour and Play for all 3 playgrounds Parks, Playgrounds and Fields Construction $ 569,752 Anticipated completion is June 2022 21028 Cameron Park- Lark Ellen House Demolition Parks, Playgrounds and Fields Planning $ 250,000 Anticipated completion is October 2022 21035 Friendship Park- Park Improvements- New playground, basketball court, entry sign, and fitness area improvements Parks, Playgrounds and Fields Construction $ 997,956 Anticipated completion is July 2022 22024 Cameron Park Restroom Improvements Parks, Playgrounds and Fields Construction $ 241,584 Anticipated completion is October 2022 22026 Walmerado Park Restroom Improvements Parks, Playgrounds and Fields Construction $ 344,000 Anticipated completion is October 2022 17022 2700 Azusa Sewer Lift Station Sewer Construction $ 3,735,166 Anticipated completion is August 2022 21010 Sewer Main Replacement- Portions Glenview Rd, Michelle St & Azusa Ave Sewer Design $ 500,000 Anticipated completion is June 2023 21011& 21012 Sewer Main Replacement - Portion of Azusa Ave. & Citrus Ave Sewer Construction $ 525,000 Anticipated completion is October 2022 21020 Residential Street Rehab Annual Program FY 20-21 Streets and Sidewalks Construction $ 2,067,200 Anticipated completion is July 2022 19006 Azusa Ave Street Rehabilitation (Vine Ave to North City Limits) Streets and Sidewalks Design (Cahrans approvals) $ 2,500,000 Anticipated completion is June 2023 22005 Residential Street Rehab Annual Program FY 21-22 (CDBG) Streets and Sidewalks Construction $ 2,477,008 Anticipated completion is September 2022 Underground Utility Dishict No.B - Merced Avenue Streets and Sidewalks Planning (SCE) $ 1,321,424 Anticipated completion is 2024 22004 Citywide Pedestrian & Vehicle Traffic Safety Improvements Streets and Sidewalks Construction $ 512,223 Anticipated completion is August 2022 Page 1 of 2 0 ylLril �u)�I�� Reed on 0611 M22 CITY OF WEST COVINA FY 2021/22 Capital Improvement Projects (CIP) Engineering Department PROJ. NO PROJECT CATEGORY STATUS PROJECT BUDGET MILESTONES I UPDATES 18040 Traffic Signal at Cameron/Banana Traffic Signal Construction $ 470,683 Anticipated completion is August 2022 21034 Fire Station No 4 Parking Lot Streets and Sidewalks Completed in March 202 $ 251,914 Construction completed, project closed out 21007 Lark Ellen and Grovecenter- Pedestrian Imp with City of Covina (West Covina is Lead Agency) Regional Completed in March 202 $ 91,200 Construction completed, project closed out. 21030 Shadow Oak Park - Restroom Facilities Completed In February 2( $ 408,600 Construction completed, project closed out 21006 La Puente Road/Forecastle - New Traffic Signal with City of Walnut (Walnut is Lead Agency) Regional Completed in January 20 $ 200,000 Construction completed, project closed out. 21027 Shadow Oak Park - Playground Parks, Playgrounds and Fields Completed in August 202 $ 340,000 Construction completed, project closed out. 20011 Residential St Rehabilitation Annual Program FY 19/20 Streets and Sidewalks Completed in August 202 $ 1,082,753 Construction completed, project closed out Page 2 of 2