12/07/2021 - AGENDA ITEM 4 - CONSIDERATION OF EXTENSION TO THE PROFESSIONAL SERVICES AGREEMENT WITH NV5, INC. FOR AZUSA SEWER LIFT STATION UPGRADE PROJECTAGENDA ITEM NO. 4 WEST" ON DATE: December 7, 2021 TO: Mayor and City Council FROM: David Carmany City Manager AGENDA STAFF REPORT City of West Covina I Office of the City Manager SUBJECT: CONSIDERATION OF EXTENSION TO THE PROFESSIONAL SERVICES AGREEMENT WITH NV5, INC. FOR AZUSA SEWER LIFT STATION UPGRADE PROJECT RECOMMENDATION: It is recommended that the City Council authorize the City Manager to negotiate and execute the Second Amendment to the Professional Services Agreement with NV5, Inc. to extend the term of the agreement through September 18, 2022. 1:7:[tl Kt I .Z11 NL I �7 i Sewage is almost universally collected by means of a gravity flow system. This project is an upgrade to a municipal sewage lift station located on Azusa Avenue. On March 19, 2021, the City and NV5, Inc. (NV5) entered into a Professional Services Agreement with NV5, a civil engineering firm, to provide construction management and inspection services for the Azusa Sewer Lift Station Upgrade Phase II Site Improvement Project. The initial term of the agreement was through September 18, 2021. On April 20, 2021, the City Council authorized the First Amendment to the agreement, increasing the total compensation to $90,000. DISCUSSION: Due to unforeseen delays caused by the COVID-19 pandemic, construction of the Azusa Sewer Lift Station Upgrade Phase II Site Improvement Project is not yet complete. It is anticipated that the field construction will be completed in Spring 2022. Staff is recommending extending the agreement with NV5 for an additional 12 months, for NV5 to continue providing construction management and inspection services for the project. Pursuant to the City's Contract Term Policy (Eff. 4-4-17), if an agreement is not amended prior to the initial term expiration date, any attempt to extend the agreement beyond the expiration date requires City Council approval. Because the agreement was not amended prior to September 18, 2021, staff is requesting that the City Council authorize the City Manager to execute the proposed amendment, to extend the term through September 18, 2022. LEGAL REVIEW: The City Attorney's Office has reviewed the amendment and approved it as to form. OPTIONS: The City Council has the following options: 1. Approve Staffs recommendation; or 2. Provide alternative direction. Prepared by: Gerardo Rojas, Economic Development Project Coordinator Attachments Attachment No. 1 - Second Amendment to Agreement with N1\75, Inc. CITY Protect Public Safety COUNCIL Enhance City Image and Effectiveness GOALS & OBJECTIVES: ATTACHMENT NO. 1 SECOND AMENDMENT TO CITY OF WEST COVINA PROFESSIONAL SERVICES AGREEMENT WITH NV5, INC. FOR CONSTRUCTION MANAGEMENT AND INSPECTION SERVICES FOR THE AZUSA SEWER LIFT STATION UPGRADE PHASE II SITE IMPROVEMENT PROJECT THIS SECOND AMENDMENT ("Amendment") is made and entered into as of September 18, 2021 ("Effective Date") by and between the CITY OF WEST COVINA, a municipal corporation ("City"), and NV5, INC., a California corporation ("Consultant"). WHEREAS, City and Consultant entered into a Professional Services Agreement on March 19, 2021 for Consultant to provide construction management and inspection services for the Azusa Sewer Lift Station Upgrade Phase II Site Improvement Project (the "Original Agreement"); and WHEREAS, on April 20, 2021, City and Consultant amended the Original Agreement to increase Consultant's maximum compensation to Ninety Thousand Dollars ($90,000.00); and WHEREAS, the Original Agreement provides for a term of six (6) months, ending on September 18, 2021; and WHEREAS, due to delays and unforeseen conditions caused by the COVID-19 pandemic, construction of the Azusa Sewer Lift Station Upgrade Phase II Site Improvement Project is not yet complete; and WHEREAS, Consultant has continued to provide construction management and inspection services pursuant to the Original Agreement; and WHEREAS, City and Consultant desire to extend the term of the Original Agreement for one (1) year, through September 18, 2022; and WHEREAS, City and Consultant intend and desire that this Amendment be effective retroactive to the Effective Date. NOW, THEREFORE, for valuable consideration, the receipt and sufficiency of which is hereby acknowledged, the parties agree as follows: 1. This Amendment shall be effective retroactive to the Effective Date. 2. The term of the Original Agreement shall be extended for one (1) year, through September 18, 2022. 3. All terms not defined herein shall have the same meaning and use as set forth in the Original Agreement. 1 NV5, Inc. Form Revised April 2020 4. All other terms, conditions, and provisions of the Original Agreement not in conflict with this Amendment shall remain in full force and effect. IN WITNESS WHEREOF, City and Consultant have executed this Amendment as of the date set forth above. CITY OF WEST COVINA David Carmany City Manager ATTEST: Lisa Sherrick Assistant City Clerk APPROVED AS TO FORM: Thomas P. Duarte City Attorney 2 CONSULTANT Todd George Chief Operating Officer Infrastructure, West NV5, Inc. Form Revised April 2020