01-21-2003 - Capital Improvement Program & Building Activity Report - 4th QTR Ending 12/31/020 City of West Covina Memorandum TO: Andrew G. Pasmant, City Manager and City Council FROM: Shannon A. Yauchzee, Director/City Engineer Public Works Department AGENDA ITEM NO. B-6b DATE January 21, 2003 SUBJECT: , CAPITAL IMPROVEMENT PROGRAM AND BUILDING ACTIVITY REPORT — FOURTH QUARTER ENDING DECEMBER 31, 2002 RECOMMENDATION: It is recommended that the City Council receive and file this report. DISCUSSION: The following Capital Improvement Program proiects were completed in the fourth auarter: DESCRIPTION BUDGETED AMOUNT City Hall — Public Area Improvements $15,000 Civic Center - Waterfall Public Art Project — Design 5,000 Concrete Bus Pads Program 2002 150,000 Del Norte Park — Replace Picnic Tables 5,000 Fire Department — Replace 2%z" Hose in all Engines 24,000 Fire Department — Replace 38 Breathing Apparatus 277,000 Sidewalk Construction Program 2002 70,000 Sunset Avenue / Francis uito Avenue - Install Hardsca e in Medians 30,000 Tot Lot Fencing at California and Palmview Parks 8,000 TOTAL $584,000 The following major Building Permits valued at $100,000 and over were issued durinL the fourth ouarter: PROJECT: VALUATION COMMENTS LOCATION/DESCRIPTION Hassen Imports Partnership $3,500,000 New Commercial Building and 1932 E. Garvey Avenue South Parking Structure Karimi Shams $350,000 New Addition to Commercial 201 N. Grand Avenue Building Rene Bobadilla $258,072 New Single Family Dwelling 1718 Gi ar Terrace Allen Brown $134,000 Addition to Single Family 928 S. Sharonlee Drive Dwelling Hassen Development $120,000 Tenant Improvement 441 N. Azusa Avenue Fremont Investment & Loan $104,000 Tenant Improvement 450 #102 S. Glendora Avenue Attached (Attachment No. 1) is a summary of Capital Improvement activity during the period from October 1 to December 31, 2002, including all projects that are under construction and projects that have been approved but not started. Also attached is the total valuation of Building Permits issued during the quarter with a year total indicated. Prepared by: Barbara Brile Administrative Analyst Attachment: Attachment No. 1 Reviewed/Approved by: Shannon A. Yauchzee Director/City Engineer ATTACHMENT NO. I I. CAPITAL IMPROVEMENT ACTIVITY — FOURTH QUARTER 2002 DESCRIPTION BUDGETED TENTATIVE STATUS/ AMOUNT COMPLETION COMMENTS, ETC. BUILDING PROJECTS Childcare Facilities — Replace Wood $16,000 January 2003 Getting bids. Rams With Metal Ramps City Hall — Enclose Elevator Lobby, 120,000 June 2003 On hold. Add Conference Room On First Floor City Yard — Storm Water Clarifier 45,000 March 2003 Design selected. NPDES City Yard — Underground Fuel Storage 60,000 May 2003 Awaiting test results. Tank Upgrades City Yard Warehouse Renovation 32,000 January 2003 In design. Civic Center — Courtyard Wall Repair 10,000 June 2003 In design. Civic Center — Security Measures — 214,000 January 2003 Under review by Police Phase 1 Department. Civic Center — Waterfall Public Art 45,000 June 2003 Art design selected. Project - Construction Community Center, Cameron Park — 4,200,000 December 2003 Demolition in progress. Building Construction Community Center, Cameron Park — 268,000 'December 2003 Out to bid. Design Community Center, Cameron Park — 50,000 December 2003 Out to bid. -Landscape Improvements Fire Station No. 1 Evaluation Study for 20,000 Pending On hold. New Location and Site Plan Fire Station No. 1 - Refurbishment 77,000 January 2003 In design. .Fire Station No. 4 — Remodel Kitchen 10,000 February 2003 In design. Fire Station No. 5 — Expansion 180,000 March 2003 In design. Fire Station No. 5 — Re -roof. 15,000 March 2003 Will bid with expansion project. Freeway Lift Stations — 55,000 July 2003 Cameron and Sunset Rebuild/Replace Storm Water Pumps stations completed; West Covina Parkway in progress. Heritage House/Park Restoration and 225,000 January 2004 Interviewed architects. Development — Construction Restroom, Design Garden and Barn Heritage House/Park Restoration and 88,000 March 2003 95% completed. Development — Repair Deficiencies Heritage House/Park Restoration and 21,000 March 2003 Interviewed architects. Development - Restroom Building Design Hurst Ranch — Community Center and 350,000 January 2003 Pending plan review and Museum Grant final agreement. Human Resources and Risk 8,500 February 2003 Received bids; awaiting Management — Replace Carpet selection. Police Department — Refurbishment of 106,300 January 2003 In design. Chief s Office — Phase H Termite Repair Program 15,000 June 2003 Ongoing. Wescove Theater — Design Performing 120,000 June 2003 On hold. Art Center TOTAL BUILDING PROJECTS $6,350,800 GENERAL PROJECTS City Hall - Energy Efficiency Upgrade $50,000 June 2003 Working with consultant. City Hall — Roof Repairs 10,000 July 2003 Ongoing as needed. Civic Center Waterfall Improvements 20,000 June 2003 Will be coordinated with art roject. I DESCRIPTION BUDGETED; TENTATIVE STATUS/ . AMOUNT COMPLETION COMMENTS, ETC. Community Services - Computer 70,000 January 2003 Reviewing software Software Recreation Program programs. Finance Department — Accounting 100,000 June 2003 Reviewing bids for Software software programs. Fire Department - Computer 69,000 February 2003 Ongoing. Automation Project Fire Department — Computer Records 110,000 June 2003 Ongoing. Management System Fire Department — Upgrade City Hall 15,000 February 2003 Design completed. Fire Alarms Fire Dispatch Alerting System 41,000 March 2003 Work to start January Replacement 2003. Maintenance District No. 4 Slope 280,000 July 2003 Ongoing. Rehabilitation National Pollution Discharge 60,000 July 2003 Ongoing. Elimination System — Best Management Practices Paseo Upgrades . 280,000 July 2003 Working on Woodgate slope in Maintenance District No. 1. Planning Department.— General Plan 100,000 June 2003 Reviewing with Planning Rewrite Commission. Planning Department — Microfiche 5,000 February 2003 Getting bids. Reader/Printer Police Department — Analysis of 15,000 January 2003 Minor repairs completed; Basement Odor , will continue monitoring. Public Works Building Division - 50,000 June 2003 Upgrading computers . Computer -Handheld and software. Public Works Building Division,- 30,000 June 2003 Ongoing. Computerized Building Permit Hardware Trash Containers at Transit Stops 10,000 March 2003 Getting bids. Citywide Walk of Fame 5,000 Pending Awaiting City Council direction. TOTAL GENERAL PROJECTS $1,320,000 PARK PROJECTS ADA Compliance - Park Barrier $ 25,000 June 2003 Bid award pending City Removals (2002) Council approval. ADA Compliance -Park Barrier 25,000 June 2003 Bid award pending City Removals (2003) Council approval. ADA Improvements in City Parks 46,200 June 2003 Bid award pending City Council approval. Center Study 16,000 Pending Awaiting sorts park. -Aquatic Butler Property Acquisition 260,000 January 2003 Pending recordation by County. Cameron Park — Rehabilitation 100,000 June 2003 Combine with ADA park improvements.. Cortez House Demolition, Irrigation, 50,000' January 2003. Demolition completed; Landscaping irrigation/meter are in, hydroseed completed. Cortez Park - Specific Plan Update 5,000 January 2003 On hold. Emergency Funds for Maintenance of 10,000 June 2003 Ongoing. CIP Projects 'Friendship Park — Rehabilitation 100,000 May 2003 Construction completed; working on irrigation. Galster Park - Specific Plan Update 8,000 June 2003 Bid award pending City Council approval. DESCRIPTION BUDGETED TENTATIVE STATUS/ AMOUNT COMPLETION COMMENTS, ETC. Gingrich Park — Rehabilitation 100,000 May 2003 'Construction completed; working on irrigation. Irrigation Improvements in Parks and 280,000 Pending Awaiting grant funding Maintenance Districts approval. Miscellaneous Park Improvements 30,000 June 2003 Ongoing. Municipal Pool Improvements 250,000 January 2003 98% completed. Orangewood Park — Roller Hockey 749,000 January 2003 Under construction. Rehabilitation/Roofing Orangewood Park — Rehabilitation 50,000 May 2003 Construction completed; working on irrigation. Palmview Park — Rehabilitation 100,000 May 2003 Construction completed; working on irrigation. Park Landscape Improvements — Install 30,000 January 2003 Under construction. Plants Around Park Signs Parks — Replace Trash Containers 10,000. February 2003 Ongoing. Ridge Riders — Security Cameras 8,000 January 2003 Cameras being installed. Ridge Riders/Maverick Field — 5,000 January.2003 On hold. -Develop Specific Plan Ridge Riders/Maverick Field — 100,000 June 2003 Compiling list of Miscellaneous Park Improvements improvements needed; - ending master plan. Ridge Riders/Maverick Field — New 16,000 -January 2003 Under construction. Park Sign/Irrigation/Landscape Ridge Riders/Maverick Field — Trash 10,000 Pending On hold for master plan. Enclosures Security Lighting Improvement 60,000 June 2003 Getting bids for Del Program (Phase I) Norte, Gingrich and Ridge Riders Parks; evaluating Friendship Park. Shadow Oak Park —.Rehabilitation 100,000 May 2003 Construction completed; working on irrigation. Shadow Oak Park — Specific Plan 5,000 January 2003 On hold. Update Shadow Oak Park — Storage Area 9,360 January 2003 In design. Shadow Oak Park — Update design 25,000 June 2003 Pending master plan plans to meet ADA compliance update. Valencia Site Acquisition 237,500 January 2003 Pending recordation of map. Walmerado Park — Upgrade 100,000 May 2003 Construction completed; working on irrigation. TOTAL PARK PROJECTS $2,920,060 STREET PROJECTS Amar Road Median Landscape $204,000 May 2003 Architect working on Improvements — east of Azusa Avenue design. Azusa Avenue Median Landscaping 450,000 June 2003 Review bids: From Nelson to Amar Azusa Avenue Median Relandscaping 232,000 March 2003 Looking at cost -saving From Garvey to Francis uito options. Azusa Avenue North — Relinquishment 85,000 October 2003 Report in progress. Azusa Avenue South — Traffic 593,000 Pending On hold for funding. Capacity Enhancement Design Azusa Avenue Traffic Capacity Study 180,000 - March 2003 Will include in weekly report to. City Council. Bus Route Street Rehabilitation 2,218,500 January 2003 99% completed. California/Plaza — Traffic Study and 20,000 February 2003 Preparing Request for Design Proposals. • DESCRIPTION BUDGETED TENTATIVE STATUS/ AMOUNT COMPLETION COMMENTS, ETC. City Entrance Signs in Medians on 185,000 June 2003 Bid award pending City Arterial Streets Council approval. Concrete Bus Pads Program (2003) 100,000 June 2003 Bid award pending City Council approval. Curb and Gutter Replacement Program 50,000 Pending On hold for funding. Hardscape Parkways Around .60,000 June 2003 Ongoing. . Schools/Parks Horse Trail — Holt to I-10 Freeway 400,000 Pending Awaiting grant funding approval. Plaza Drive from. California to Vincent 200,000 May 2003 Pending design. Avenues — Widening Rowland Avenue Median 175,000 June 2003 Preparing Request for Relandscaping ' Proposals. Safe Routes to Schools Study 100,000 June 2003 Awaiting grant funding approval. Sidewalk Construction Program (2003) 40,000 February 2003 In design. Street Barrier Removals 50,000 February 2003 In design. Street Rehabilitation — Annual Program 848,000 June 2003 In design. Sunset Avenue Between Fairgrove and 30,600 February 2003 Architect working on ,Francis uito — Parkway Landscaping design. Underground Utility District No. 6 45,000 February 2003 Edison 99% completed; Cameron Avenue Residential -cable and telephone Conversions (Phase 1) being relocated. Urban Forestation Program 50,000 June 2003 Ongoing. TOTAL STREET PROJECTS $6,316,100 TRAFFIC PROJECTS Flashing Beacons at Various $320,000 June 2003 Awaiting grant funding Elementary School Sites a roval. Public Safety Intersection Intervention 150,000 Pending On hold for funding. System - Traffic Signal'Loops Replacement and 50,000 June 2003 Under design. Rewire Traffic Signal Modifications — Sunset 80,000 March 2003 Working on and Cameron Avenues specifications for left - turn. Traffic Signals — Minor Modifications 50,000 June 2003 Installing confliet (2002), monitors. Traffic Signals — Minor Modifications 50,000 June 2003 Installing -conflict (2003) monitors. Uninterruptible Power Supply for 160,000 June 2003 Scheduling start date for Traffic Signals . construction. TOTAL TRAFFIC SIGNAL $860,000 PROJECTS YOUTH SPORTS PROJECTS Cortez Park — Safety Netting $26,000 Pending Bids rejected; project on hold. . . Del Norte Park — Repair Backstop on 6,000 January 2003 Under construction. T-Ball/Farm Field Del Norte Park - Replace Fence, Install 15,000 January 2003- • Getting bids. Removable Fence at T-Ball Field Edgewood Middle School — Fitness. 15,000 June 2003 Awaiting school district Course approval. Giano Intermediate School — Baseball 0,500 Pending Awaiting disposition Lighting, Electrical from Rowland School District. DESCRIPTION BUDGETED TENTATIVE STATUS/ AMOUNT COMPLETION COMMENTS, ETC. Maverick Field — Foul Ball Safety 50,000 Pending Bids rejected; project on Netting hold. Shadow Oak Park — Extend Safety 12,000 Pending Bids rejected; project on Netting Along 3Td Base hold. Shadow Oak Park — Netting Over Top 6,000 Pending Bids rejected; project on of Backstop hold. Sunset Field — Netting Over Snack Bar 6,000 January 2003 Reviewing bids. Walmerado Park — Drainage in Front 1,000 January 2003 In design. of Snack Bar Door West Covina High School - Basketball 125,000 February 2003 Awaiting State plan and Courtyard Lighting check. TOTAL YOUTH SPORTS $271,500 PROJECTS GRAND TOTAL $18,038,460 II. TOTAL BUILDING PERMIT VALUATION TIME PERIOD YEAR TOTAL VALUES Fourth Quarter 2002 $8,985,239.30 2001 $14,230,696.20 Total Year -To -Date (1", 2° , 3r , and 4` 2002 $45,219,815.04 Quarters) 2001 $42,394,012.60 5