01-21-1997 - Capital Improvement Program & Building Activity Report - 4th Qtr. 1996City of West Covina
.x
`Memorandum
AGENDA
TO: City Manager and City Council
ITEM NO. C-6a
FROM: Patrick J. Glover
City Engineer/Public Works Director DATE January 21, 1997
SUBJECT: CAPITAL IMPROVEMENT PROGRAM AND BUILDING ACTIVITY
REPORT - FOURTH QUARTER 1996
SUMMARY: This report is to provide the City Council with a summary
of Major Building Permits issued and Capital
Improvement Activity during the quarter ending
December 31, 1996.
RECOMMENDATION
Receive and file.
P,Atrick J. der
City Engineer/Public Works Director
PJG:TM:WD:YA:gc
Attachments
r
1
s
I. CAPITAL IMPROVEMENT
ACTIVITY - FOURTH QUARTER 1996
PROJEGT DESCRIPTION
/LOCATION`
BUDGET <
ACTIVITY
Police Department Computers
$500,000
Being implemented.
Bus Shelters Rehabilitation/Replacement
$80,000
Design phase.
Civic Center Bandshell and Veterans Wall
$175,000
Being designed.
Pump Stations - Aroma Water Line & Pump
$500,000
Construction starts
Station to Westridge
January 1997.
Reservoir Coating -
Reservoir 1 and 2 &
$220,000
Reservoir 1 completed.
repairs
Reservoir 2 work to
commence.11/96.
Orange / San Bernardino
Road Traffic Signal
$60,000
Working on right-of-way
acquisition.
Shadow. Oak Drive- slopes
landscaping
$80,000
Plans & specs approved.
(Combine with 94206 &
95229) .
Maintenance District No. 1
- Slope
$250,000
Kimberly portion in
Rehabilitation
maintenance phase.
(Combine w/94124).
Maintenance District No. 4
- Slope
$60,000
Plans and specs
Rehabilitation
approved. (Combine with
94204 & 95229)
Energy Efficiency Upgrading
Thermal & Parking Structure
/ City Hall
Lights
$100,000
Lights ordered.
(Combine with 95303)
Shadow Oak Center - Repair moveable
$22,000
Ready for bid.
partitions, repaint, dry wall, concrete slab
Shadow Oak Grading, Irrigation and
$150,000
Plans and specs
Landscaping Tennis Court Area
approved. Project ready
to bid. (Combine with
94204 & 94206)
NPDES
$60,000
Work in progress.
Pavement Management System
$60,000
On -going. City wide
survey complete.
Sidewalk Construction & Handicap
ramps at
$155,000
Design in progress.
Various Locations
Minor Traffic Signal Modifications
$354,000
Some work completed.
Design of remainder in
progress.
Street Rehab - Slurry
Various Locations
$267,000
Completed-.
Glendora Avenue Expansion
$1,500,000
Near completion.
Walmerado Restroom Facilities Expansion p
$90,000
Work, in .progress.
Hollencrest - Portable Snack Bar
$58,000
Design in progress.
MD #4 Slope Restoration I- Shadow Oak Villas
$60,000
Slope investigation in
Ill
progress.
Palm View Park - Tot Lot
ADA Conformance
$120,000
Completed.
c:\msoffice\winword\agenda\4thqt.doc
2
•
PROJEGT: DESCRlPT1, K.f LOCATION
BUDGET
AGTiV1TY
Galster Park - Restroom Modifications, Barrier
$40,000
Design complete.
Removal
MD# 4 - wall repair and open space surface
$130,000
Balance will be returned ,
drainage correction - W/O Stephanie S/O
to MD4 reserves.
Stacey
Renault Slope Planting - Shadow Oaks Villas
$35,000
Plans and Specs ready.
III
Waiting for Risk
Management approval.
Ridge Rider Improvements
$75,000
Work in progress.
Simulator and Expansion Simulator Room
$250,000
Design complete.
(Combine w/96303).
Simulator Room Restrooms
$50,000
Design complete.
(Combine w/96302).
Street Rehabilitation Program
$750,000
Locations being
compiled.
Lark Ellen Ave. Rehab - from 1-10 fwy to
$660,000
Waiting for pavement
Cameron, Merced to Francisquito and
evaluation report. To be
Maplegrove to Amar
combined w/97107
Curb and Gutter Repairs
$40,000
Being advertised.
Streets Barrier Removal Program
$707000
Locations being
identified.
Sunset Ave. Rehab from
$370,000
To be combined with
1-10 fwy to north City limit
PP97103 - (See
comments for that
project).
Rowland Ave. Rehab
$170,000
Waiting for pavement
from Vincent Ave to Azusa
report.
Merced Ave Rehab
$120,000
Waiting for pavement
from Sunset to Willow
report.
Street Rehab (Bus Routes)
$300,000
Combined with SP97108
and 97109 to extend
project limits.
Azusa Avenue Landscape Over Hill
$130,000
City to determine scope
and limits of work..
Trash Handling Facility for City Yard (NPDES)
$35,000
No progress.
Handicap Parking Signs
$10,000
Work in progress
(ADA) for City Parking Lots
First Phase of City GIS
$265,000
Implementation study in
(Plan, Hardware, Software, Data)
progress.
Cortez Park American Little League -
$85,000
Work in progress.
relocate lights, extend outfield fence, new
bleachers
Del Norte Park West Covina National Little
$45,000
Plans completed.
League - snack bar improvements
Hollencrest Middle School
$12,000
Waiting for league &
South Hills Little League
school district approval.
Light for Maverick Field (adjacent to Ridge
$150,000
Work starts January
Riders) Maverick Development Group
1997.
Heritage Gardens Additional funding for
$60-1000
Work in progress.
Landscaping -Phase 1
Aroma Ball Field(s)
$200,000
No progress.
Development for park use.
Edgewood.Middle School
$155,000
Waiting for OSA and
Expand Parking Lot
school district approval.
(currently 23 spaces)
c:\msoffice\winword\agenda\4thgt.doc
0
Orangewood Park - Basketball Lighting
$35,000
Plans complete.
Cameron Youth Center Rehab including
restroom addition and modifications
$155,000
Design in progress.
Wescove School Portable Classrooms
$70,000
Fabrication phase.
California School Portable Classrooms
$70,000
Fabrication phase.
Palm View Park Center Restroom Addition
$40,000
Need confirmation of
school district action.
New Roof for Fire Station' -No. 4
$30,000
Work in progress.
Radiators for City Hall
Emergency Generators
(fund from Energy Savings)
$30,000
Consultant located.
Preliminary report
prepared.
Westside Historical Facility
$100,000
Preliminary plans
completed.
Amar Road Guardrail
$50,000
Design in progress
c:\msoffice\winword\agenda\4thgt. doc
4
t
II. MAJOR BUILDING PERMITS ISSUED FOURTH QUARTER 1996
(Over $160,000)
Lee/Prospero Partnership
$433,669
Single Family Dwelling
703 Prospero Drive
First Financial Credit Union
$210,000
Tenant Improvement
1600 W. Cameron
Pacific Community
$1,921,419
Single Family
Tract 35930
Dwelling(12)
Brookfield Homes
933,872
Foundation Only (3)
Tract 47809
Westfield/Babies `R Us
$150,000
Storage Racks
2753 Eastland Center Drive
Edwards Theatre
$187,000
Fountain
265 S. Glendora Ave
L.A. Cellular
$160,995
Permit 90-722 valuation
2640 E. Garvey Ave'
increase
Eastland Tower Partnership
$177,00
Tenant Improvement
423 N. Azusa Avenue
Tr Brell
$140,000
H.V.A.C. retrofit
1509-1521 Cameron
Westfield/Oshmans
$146,00
Storage Racks &
837 Plaza Drive
Shelving
III. TOTAL BUILDING PERMIT VALUATION