01-07-1992 - Construction Activity ReportCity of West Covina Memorandum TO City Manager and City Council FROM Harry W. Thomas, City Engineer AGENDA ITEM NO. C-5a SUBJECT: CONSTRUCTION ACTIVITY REPORT DATE January 7, 1992 This report describes current status of Citywide Construction activity. Attached for your consideration is the above -mentioned Report. Harry W. Thomas Public Works Division Manager/City Engineer HWT:TMM•lw. cipgrtly CAPITAL IMPROVEMENT PROJECTS QUARTERLY STATUS REPORT DECEMBER 31, 1991 Page 1 of 5 --------------- --------------- PROJECT : LOCATION / BUDGET STATUS / COMMENTS DESCRIPTION / NUMBER Woodside Village S 130,787 Work in progress Landscape Conversion in MD #4 MP-87108 & MP-88109 Cortez Street: Citrus to Grand $1,765,000 Contract awarded Widening / Reconst. / Storm Drain SP-87115 Reservoir #1. $ 149,173 Not started Painting Exterior WP-87120 Amar Road: $1,780,695 Work in progress Water Main: Phase I WP-87126 Amar Rd. s 680,000 Design completed Water Main : Phase II WP-92113 ; WP-87126 Azusa Avenue : Southerly of Amar $ 102,583 Contract awarded Replacement of sewer lift station SS-87133 City Yard :. Civic Center S 526,788 Work in progress Fire Station Replacement &/or monitering of underground fuel tanks MP-87148 City Yard. $ 26,402 Work in progress Replacement / refurbishment of Fuel Delivery System MP-87152 Page , 2 of 5 ------------ PROJECT LOCATION / BUDGET STATUS / COMMENTS DESCRIPTION / NUMBER', Fire Station #2 / Cortez Park S 842,516 EIR preparation Replacement of fire station with in progress standardized facility GP-87308 Cortez Park $1,400,000 Work in progress New Multi -Purpose Center with expanded parking GP-87309 Galster Park S. 100,000 On hold Improvement per specific plan PP-88201 Woodside Village S 25,000 RFP,to be sent out Water Leak Detection WP-90103 Fashion Plaza S 275,000 Alignment adopted Construct New California Ave. Design in progress SP-9010.4 Azusa Ave/Cortez to Francisquito S 25,000 Work in progress Remove Block Median Planters MP-90110 Vincent Ave.: Garvey to Garvey S 110,000 Work in progress Underground Utility Distribution MP-90111 Badillo Ave. & Grand Ave. S 243,150 Design completed Water Transmission Main WP-90118 MD# 1,2,4,6,and 7 S 99,000 Work in progress Survey Monumentation MP-90122 City Parks S 81,340 Design in progress Equipment Replacement MP-90124 & PP-91202 Page 3 of 5 PROJECT : LOCATION / BUDGET STATUS / COMMENTS DESCRIPTION / NUMBER City Parks S 28,000 Design completed Light Standard Replacement PP-90126 & PP-91203 Cortez Park S 20,000 On hold Upgrade Irrigation System PP-90201 California Ave $1,000,000 Design in progress West Covina Pkwy to I (10) Underground Utility MP-91101 Woodside Village S 40,000 Not started Water System Telemetry WP-91111 Reservoir #2 S 501000 Design completed Altitude valve Installation WP-91112 Various Locations 119,000 Contract awarded Signal. coordination MP-91126 City Parks $ 75,000 On hold Cultural facili.'ty PP-91204 Shadow Oak and Cameron Parks $ 31,000 Design in progress Re -roof Centers GP-91304 City Hall $ 50,000 Work in progress Elevator, Rehab. GP-91305 Page 4 of 5 ------------ PROJECT : LOCATION / BUDGET STATUS / COMMENTS DESCRIPTION. / NUMBER City wide S 60,000 Work in progress PMS Update SP-92101 City wide S 685,000 Design in progress Street Rehabilitation SP-92102 City wide S 30,000 Work in progress Urban Forestation MP-92103 City wide S 50,000 Contract awarded Repair/Replace Curb & Gutter SP-92104 City .wide S 25,000 Design in progress Priority Sidewalks SP-92105 City wide S 175,000 Contract awarded Concrete Bus Pads SP-92106 City wide $ 50,000 Design completed Minor Traffic Signal Mod. TS-92107 Grand & Valley S 40,000, Work in progress Interconnections • TS-92108 La Puente/Sentous S 100,000 Design in progress Traffic Signal TS-92109 City wide. $ 30,000 Design in progress Sewer Extent.ion SS-92110 _PROJECT : LOCATION/ DESCRIPTION/NUMBER BUDGET Grand Ave. $ 400,000 Water Main WP-92112 City Yard $ 16;000 Wash Rack MP-92114 Tuesday/Wednesday Slope $ 50,000 Drainage Control MP-92115 MD#6 . $ 25,000 Lot Landscape MP-92116 MD#7 $ 15,000 Fence & Landscape MP-92117 MD #: 4,6,& 7 $ 30,000 Survey Monumentation MP-92118 Palmview Center S 10,000 Reroof PF-92201 City Parks 50,000 Replace Bleacher Seats o PP-92202 Page 5 of 5 STATUS/COMMENTS Design completed Design in progress 'D"e.sign completed Design in progress Not started Work in progress Design in progress Work in progress